Business Impact Analysis

Resilience · 3 min read

What would hurt most?

If your house were on fire and you had two minutes, what would you grab? Probably not the toaster. You’d grab the things that are irreplaceable, or that you’d need first thing tomorrow.

A business impact analysis (BIA) asks the same question of an organisation: which processes matter most, how quickly does the damage grow if they stop, and what do they depend on? It’s the foundation of the whole BCP. Recovery strategies, priorities and budgets all come from it.

The BIA is about impact, not threats. Working out what could cause a disruption is the risk assessment.

The steps

List processes, gather information, assess impact over time, set objectives, find dependencies, prioritise and approve.
  1. List the business processes and their owners.
  2. Gather information from process owners and key users through questionnaires, interviews and workshops.
  3. Assess impact over time: what happens after an hour, a day, a week? Consider money, regulators, customers, reputation, operations and safety.
  4. Set recovery objectives for each process: maximum tolerable downtime (MTD), recovery time objective (RTO), recovery point objective (RPO).
  5. Find dependencies: IT systems, data, people and skills, suppliers, premises, other processes. Miss one, and recovery stalls.
  6. Prioritise processes for recovery.
  7. Validate and approve with senior management.

Four levels of criticality

Critical, vital, sensitive and non-critical, from least to most tolerant of downtime.
CategoryMeaning
CriticalCan’t be done unless replaced by identical capability. Very low tolerance for interruption; very high cost.
VitalCan be done manually, but only for a brief period.
SensitiveCan be done manually for an extended period at tolerable cost, with extra staff or effort.
Non-criticalCan be interrupted for a long time at little or no cost.

The difference between critical and vital is whether it can be done by hand at all. Between vital and sensitive, it’s for how long.

IT systems take their priority from the processes they support. A system behind a critical process is critical, even if IT thinks of it as a minor application.

Finding the right spend

Two costs pull in opposite directions:

Cost of downtime rises with time, cost of recovery falls, and total cost is lowest in between.
  • The cost of downtime rises the longer a process is down.
  • The cost of recovery falls as you allow more time (a mirrored site costs far more than a cold site).

The best strategy sits where the total is lowest, as long as it’s still within the MTD. A very short RTO is only worth paying for if downtime is very expensive.

Business decides, IT follows

  • Process owners and key users supply the information and define the impacts.
  • IT describes system dependencies and current recovery capability.
  • Senior management validates and approves the priorities.
  • The BCP coordinator facilitates.

Example. IT assumed the email system was its top recovery priority. The BIA showed the customer order system had an MTD of four hours, because large customers’ contracts include penalties for missed deliveries, while email could be down for a day using phones and a backup messaging tool. Recovery priorities and spending were changed.

Review the BIA after significant business changes, and periodically.

How the exam asks about it

If the question asks…The answer is usually…
Primary purpose of a BIAIdentify critical processes and the impact of disruption, to set recovery priorities
Main source of BIA informationBusiness process owners and key users
Output used to choose recovery strategiesRTO, RPO and MTD for each process
Process that can be done manually only brieflyVital
How the optimal recovery strategy is foundBalancing the cost of downtime against the cost of recovery
When to update the BIAAfter significant business changes and periodically

In short

  • The BIA identifies critical business processes, the impact of their disruption over time, and the resources they depend on.
  • It produces recovery priorities and objectives: MTD, RTO and RPO for each process and supporting system.
  • Impacts include financial loss, regulatory penalties, customer harm, reputational damage and safety.
  • Information comes from process owners through questionnaires, interviews and workshops, and is validated with senior management.
  • Criticality categories: critical, vital, sensitive and non-critical, based on how long a process can be down and whether manual workarounds exist.
  • Comparing the rising cost of downtime with the falling cost of recovery helps find the optimal recovery strategy.
  • The BIA should be reviewed when the business changes significantly, and periodically.

Exam traps

  • The BIA is about business impact, not threats; identifying threats is the risk assessment.
  • Process owners, not IT, are the main source of BIA information.
  • A shorter RTO means a more expensive recovery strategy; the BIA balances the two.
  • IT systems inherit recovery objectives from the business processes they support.
  • Dependencies (suppliers, other systems, key people) must be identified, or recovery will stall.

Slides

Click the slide and use the arrow keys. F toggles full screen.

CISA · Domain 4 · Resilience

Business Impact Analysis

Working out what would hurt most if it stopped, and how fast: the BIA steps, the four criticality levels, and the cost curves that point to the right recovery strategy.

1 / 9